This underground stormwater detention system was a pivotal aspect of the project, serving a dual-purpose by not only effectively managing stormwater but also allowing for the creation of four additional buildable lots on the western side of the property. This innovative solution replaced the conventional open detention pond, optimizing land use in the neighborhood.
Beyond stormwater management, the project included extensive infrastructure work, encompassing the installation of over 2000 linear feet of sewer, water, storm, and electrical lines. Additionally, asphalt paving and curbing were implemented throughout the neighborhood to enhance accessibility and functionality. The entire endeavor, managed in collaboration with Benesch Civil Engineer for June Lake, spanned 8 months, concluding in 2022.